Tiling is finished, Fixing invoice has been received, and we have a garage door!

We met with Dean at midday today to have a walk through. The first thing I noticed was that the security fencing is down.

The second thing was the garage door has been installed!

Photo 13-4-17, 12 10 30 pm

We had a walk around the outside of the house – where we noticed that the rear tap hasn’t been installed yet, and the outdoor tiling looks fantastic.

Photo 13-4-17, 12 13 33 pm

Inside, all the tiling has been completed as well. The tiler (Harry) did a great job of lining up the tiles going up the walls and bath hob to match the floor tiles. The recess looks great, the laundry looks great, and I am so happy that the splash back looks great as well (I was a little worried!)

Next week it’s pre-painting, we have organised an external inspection for Monday and I am heading back to the block to sign a variation with Dean on Monday afternoon. We have queried and then requested that our driveway be cut into the gutter – it’s a pain driving over the gutter onto the driveway at our current place!

We also have to head back there over the next couple of weeks and move the bricks that we want to the back of the house, or else they’ll be thrown out. We are getting a box of each tiles put aside from the leftovers as well.

We have electrical and plumbing fit out, carpet and laminate flooring, security screens and roller blinds to go, as well as the driveway and painting. Still no updated PCI date, still being told the end of June, but we’ll see!

Advertisements

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s